| Province | Subbasin | % |
|---|---|---|
| Intermountain | Pend Oreille | 100.00% |
| Previous: | Next: |
|---|---|
| 74975: 1995-001-00 EXP KALISPEL RESIDENT FISH PROGRAM HATCHERY |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Completed Environmental Documentation | B: 165. Obtain required environmental clearance to implement affected Work Elements | 02/01/2019 | 02/01/2019 | |
| Maintain Hatchery Operations | C: 61. Maintain day-to-day hatchery operations | 02/01/2019 | 02/01/2019 | |
| Produce TRBT | D: 176. Produce KTFH raised TRBT for Kalispel Member harvest | 02/01/2019 | 02/01/2019 | |
| Maintain fish health | E: 60. Maintain fish health of hatchery raised fish | 02/01/2019 | 02/01/2019 | |
| Put and Take Fishery | F: 187. Tribal Member harvest of KTFH raised TRBT | 02/01/2019 | 02/01/2019 | |
| Kalispel Tribal Fish Hatchery Production Plan | G: 174. Kalispel Tribal Fish Hatchery Production Plan | 06/15/2018 | 05/31/2018 | |
| Kalispel Tribal Hatchery and Natural Resource Department Outreach and Education | H: 99. Kalispel Tribal Hatchery and Natural Resource Department Outreach and Education | 02/01/2019 | 02/01/2019 | |
| Coordinate with CCT on shared salmon harvest | I: 191. Coordinate with CCT on shared salmon harvest | 02/01/2019 | 02/01/2019 | |
| Attach Progress Report in Pisces | J: 132. Submit Progress Report for the period February 2018 to February 2019 | 02/01/2019 | ||
| Hatchery Administration and Management | K: 119. Prepare Draft Scope of Work and Budget for FY 19 | 02/01/2019 | 02/01/2019 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Trout, Rainbow (Oncorhynchus mykiss) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 185 | Periodic Status Reports for BPA | 02/02/2018 | ||||||
| B | 165 | Obtain required environmental clearance to implement affected Work Elements | 02/02/2018 | ||||||
| C | 61 | Maintain day-to-day hatchery operations | 02/02/2018 | ||||||
| D | 176 | Produce KTFH raised TRBT for Kalispel Member harvest | 02/02/2018 | ||||||
| E | 60 | Maintain fish health of hatchery raised fish | 02/02/2018 | ||||||
| F | 187 | Tribal Member harvest of KTFH raised TRBT | 02/02/2018 | ||||||
| G | 174 | Kalispel Tribal Fish Hatchery Production Plan | 02/02/2018 | ||||||
| H | 99 | Kalispel Tribal Hatchery and Natural Resource Department Outreach and Education | 02/02/2018 | ||||||
| I | 191 | Coordinate with CCT on shared salmon harvest | 02/02/2018 | ||||||
| J | 132 | Submit Progress Report for the period February 2018 to February 2019 | 02/02/2018 | ||||||
| K | 119 | Prepare Draft Scope of Work and Budget for FY 19 | 02/02/2018 |